WAFI CITY CENTRE – DCCP ONE



District Cooling System for a total 8,100 TR capacity for Wafi City DCCP ONE Project.

US Green Building Council has certified Leadership in Energy and Environmental Design (LEED) Gold Rating for energy efficiency, environment, water conservation and use of recycled products and renewable energy to protect the environment during operation.


 
PROJECT DETAILS
 

Services
Client
Engineers & Project Managers
Total Tonnage

:
:
:
:
District Cooling System
M/s MKM Commercial Holdings LLC.
M/s Green Technologies.
8,100 TR Capacity Chiller Plant.
CHILLERS BAY

 
PLANT CONFIGURATION
 
  • 8100 TR Capacity Chiller Plant
  • 4nos. Primary CHW Pumpsets
  • 4nos. Secondary CHW Pumpsets
  • 4nos. Condenser water Pumpsets
  • 5nos. Cooling Towers
  • 2nos. Air separators
  • 1 no. Expansion Tank
  • 4nos. VFDS
  • Automatic Chemical Dosing System
  • Cooling Tower Make up water pump system
  • 4500 TR Energy Transfer Stations in Hotel
  • Sump Sweeper System
  • Refrigerant Monitoring System
  • Refrigerant Recovery System
  • 6nos. 11/0.4 kV & 11/3.3 kV Transformers
  • MV Switchgear
  • LV Panels & Switchgear
  • Fire Alarm & Fire Fighting System
  • Integrated Building Management System
  • Lighting and Power Distribution System
  • Emergency Lighting System
  • Portable Water
COOLING TOWERS   SUMP SWEEPER SYSTEM

 

 
PUMP ROOM   L V PANEL

 

M V PANEL