ABU DHABI COMMERCIAL BANK



The state-of-the-art Electromechanical facilities are provided including ELV system such as, PA/VA System, Security System, Structured cabling network, Building Management System, Inergen Gas System, Fire Alarm and Fire Fighting Systems.

120 Meters high, Abu Dhabi Commercial Bank Head Quarters (ADCB) building is one of the impressive tall structures in Abu Dhabi.

 

 

PROJECT DETAILS
 

Client
Consultant
Project Management
Contract Duration

:
:
:
:
Abu Dhabi Commercial Bank
M/s. Architecture & Planning Group
M/s. Turner Construction International
18 Months
 
SCOPE OF THE PROJECT
  • 5 x 350 TR capacity chillers
  • 300,000 sq.ft phenolic pre insulated ducting
  • 55 Nos. Variable Speed AHUs
  • 130 Nos. FCUs
  • 600 Nos. VAV Boxes
  • 10 Kms of custom made Linear Bar Grills
  • 2 Nos. FAHUs & TEXUs with heat recovery system
  • 6 way 11kV nigear Switchgear
  • 12,000 Nos. Light fittings
  • 2 sets of 1000 kVA Generators
  • UPS
  • 12,00 Data/Voice Points
  • Bulding Management System
  • Fire Alarm/Public Alarm System
  • 75 GPM Fire Fighting Pump
  • 2,500 Nos. Sprinklers
  • Deluge – Pre-Action System
  • Inergen System
  • Multi Media & Catridge Centralized Water Filtration System
  • 3 Levels of Car Park for 150 Cars
 
CHILLER YARD   BMS & SECURITY SYSTEM CONSOLES