MALL OF THE EMIRATES



The District Cooling System and Primary MEP works for Mall of the Emirates at Sheikh Zayed Road.

The District cooling plant is designed for a total capacity of 14,950 TR located in a chiller Plant room feeding Chilled Water to 3.9 million sq.ft development which consists of Carrefour Hypermarket, Snow Centre, West Hotel and 700 outlets.

The District cooling System has been designed for a total of 14,950 TR housed in a Chiller Plant room with13 Nos. Centrifugal Chillers each of 1150 TR capacity and serving chilled water to the entire malldevelopment through 4 kilometers of buried pre-insulated MS Piping.

From the same plant room, filtered water for the entire mall as well as water for the Fire Fighting System is supplied through 2.2 kilometers of high-density polyethylene buried pipes.


PROJECT DETAILS

Services
Client
MEP Consultants
Project Management
Commencement
Completion
Total Tonnage

:
:
:
:
:
:
:
District Cooling System + Primary MEP Works
M/s. Majid Al Futtaim Investments LLC
M/s. WSP Middle East
M/s. Mace International Ltd
January 2004
September 2005
14950 TR
CHILLERS BAY

FASCINATING FIGURES
  • 13 Nos. x 1150 TR Capacity WCM with auto cleaning System
  • 8 Nos. Primary Chilled Water Pumps
  • 10 Nos. Condenser water pumps
  • 12 Nos. Cooling Towers
  • 5 Nos. Sand Separators
  • 1 No. Pressurization Unit
  • Automatic Chemical dosing system
  • 3 Nos. Cooling Tower Make up water pumps
  • Automatic tube cleaning system for Chillers
  • GRP Piping for Condenser Water
  • 4 KM of Buried CHW piping with leak detection system
  • Fire Pumpset
  • Domestic water transfer & booster pumpsets
  • Water filtration set incl.multimedia & carbon filters
  • 2.2 Km high density polyethylene buried pipes for water services and Fire Fighting
  • 94MW LV connected load from 85 Nos. 1500 kVA Transformer
  • Fire Alarm & Fire Fighting System
  • Emergency Lighting System
COOLING TOWERS FILTRATION UNIT FOR WATER SUPPLY

FIRE PUMPSETS L V PANEL

SAND SEPARATOR CONDENSER WATER PUMPS

COOLING TOWER MAKE UP WATER PUMPS GRP PIPING CONNECTION

PRESSURIZATION UNIT CHILLED WATER PUMPS

GRP PIPING CONNECTION TO CHILLERS CHILLER CONNECTION PIPING

CHILLED WATER PIPING CONNECTIONS TRANSFER & BOOSTER PUMPS